We were pleased to receive an update today from Sr. Emperatriz regarding the process of the La Inmaculada Well Project.
She reports some days were lost in the excavation and building process as a result of the conflict in Nicaragua. They have now reached water! The next step will be constructing walls around the dig site to keep the well from collapsing and connecting pipes and electrical systems. The water storage tank and well house have already been built. These items will need to be connected into the system as well
We hope to receive more pictures soon. When we do we will be sure to share them on our social media.
Thank you to everyone who donated to this vital project.